Plans finalized for Moore emergency center

NORMAN — Moore Medical Center is going modular, and the temporary facility will open in late November or early December, Norman Regional Health System officials said Friday.

Design changes and a calculation error by the leasing company resulted in a modified contract for the temporary emergency department and outpatient lab. Those changes, along with a cost reduction due to equipment donations by Sona Site and Space Labs, mean the fully-equipped, new facility will cost less than anticipated.

Johnson Portable Buildings — the company that provided the temporary facility for the Joplin, Mo., hospital — will lease the modular units to the Norman Regional Health System for 24 months at a cost of $61,338 per month for a total cost of $1,472,112. The delivery, installation and removal charge is an additional $245,000, the storm shelter $50,00 and utilities and site prep are $100,000.

The cost of equipment, which will be retained for use at the new permanent site, is $523,916. The health system is saving $429,498 because of the donation of ultrasound equipment by Sona Site and the loan of monitoring equipment by Space Labs.

New monitoring equipment will be needed for the permanent facility, but additional equipment would have been needed anyway. The insurance will cover that cost.

The total cost of the temporary facility rings up at $2,595,888.

The emergency and urgent care treatment facility will have a CT, X-ray and lab, which means outpatient lab services can be performed in Moore while the new hospital is being built.

NRHS CEO David Whitaker said focus groups have been completed and the information gathered in those meetings will be turned over to the master facility committee. The focus groups collected input on how best to serve Moore. The master facility committee will begin working with architects on a project design.

Whitaker said Moore Medical’s labor and delivery staff have been fully incorporated into the HealthPlex for the time being. Their services are needed with the increase in volume created by the loss of Moore Medical.

Text Only | Photo Reprints
Government
  • Council OKs $48.8M contract for wastewater plant upgrades

    The Norman City Council awarded a $48.8 million project for wastewater treatment plant upgrades Tuesday. The council accepted a $50.3 million low-interest loan from the Clean Water State Revolving Fund....

    April 23, 2014

  • Craft breweries new category of Okla. made

    Norman will now recognize Oklahoma brewers to allow craft breweries to operate under special licensing. On Tuesday, the city council approved the creation of an additional category of Oklahoma Brewer to the city’s fee schedule for ...

    April 23, 2014

  • City home first to include gray water system

    Neighbors are likely to be green with envy when Allen and Sallie Ahlert have a beautiful lawn and garden without paying extra for city water in the future. That’s because the Ahlerts are including a gray water system in the new home they ...

    April 22, 2014

  • Anti-abortion picketers target Moore schools

    MOORE — Moore City Council member Robert Krows said problems with picketers at schools have gravitated from Norman to Moore and parents are concerned....

    April 22, 2014

  • Oklahoma receives $77.18M tobacco settlement payment

    Oklahoma recieved $77.18 million in annual payments from the tobacco industry under the national Master Settlement Agreement. With the latest receipts, Oklahoma has received $1.16 billion since payments began in 1999. State Treasurer Ken ...

    April 22, 2014

  • Congressman Cole reflects on recovery

    Congressman Tom Cole’s home in Moore was not hit by the May 20 tornado but it came pretty close. His wife has made it clear she wants a saferoom, he said. In a visit to the Transcript on Friday afternoon, Cole talked about tornado ...

    April 19, 2014

  • Oklahoma Water Resources Board grants Norman low-interest loan for facility upgrade

    Norman has been authorized for a $50.3 million loan from the Oklahoma Water Resources Board to fund Phase 2 of the Norman Water Reclamation Facility upgrade. “It’s the single largest loan OWRB has made,” Norman Mayor Cindy Rosenthal said. ...

    April 17, 2014

  • General fund continues to decline as expenses exceed anticipated revenues

    Norman’s expenses will again outstrip projected revenue in the current budget before the city council. The budget for the fiscal year that starts in July and ends June 30, 2015, projects $210,982,020 in total revenues and $213,436,778 in ...

    April 16, 2014

  • County hears presentation on employment opportunities

    The Cleveland County Board of Commissioners listened to a presentation Monday to consider partnering with a nonprofit that provides employment opportunities for prison inmates re-entering the community. Patrick Viklund, Center for ...

    April 15, 2014

  • Drilling operation shows policy gap

    While Norman residents are being encouraged to use rain barrels, a Texas oil and gas company is pumping thousands of gallons of treated drinking water into the ground. The Oklahoma Corporation Commission controls permits for drilling, ...

    April 12, 2014