I-35 traffic shifted today

NORMAN — Allen Contracting and Manhattan Road and Bridge Company, under contract with the Oklahoma Department of Transportation on Friday shifted the two southbound lanes of I-35 west onto their new configuration.

The traffic shift will allow the contractor to construct a portion of the permanent roadway of I-35 for both north and southbound traffic. The traffic shift was to have been completed by 6 a.m. today.

Additionally, beginning on Tuesday, Jan. 7, Manhattan Road and Bridge Company will begin to place the remaining bridge beams for the Main Street Bridge over I-35.

The work, which will require the temporary closure of lanes on I-35, will be completed between the hours of 8 p.m. and 6 a.m.  During the day, all four lanes on I-35 will be open to traffic. Weather permitting, the contractor expects to have all the beams installed by 6 a.m. on Thursday.

Construction on the I-35/Main Street Interchange Project began Jan. 7, 2013 and is expected to be completed by May of 2014.

In a related project, Sherwood Construction Company shifted the two northbound lanes of Interstate 35 one lane to the west. The shift placed traffic on the alignment needed to construct the State Highway 9 Interchange Project. 

Traffic was reduced to one lane northbound temporarily during the lane shift to provide the contractor safe working distance to remove the barrier wall.  Both northbound lanes were to be reopened by early today.

Construction of the $12 million State Highway 9 Interchange Project over I-35 began Nov. 18, 2013.  As a part of this construction, Sherwood Construction Company will also build the first phase of the Lindsey Street Widening Project drainage structure. 

This is the southernmost section of the drainage structure that will eventually remove the stormwater runoff from Lindsey Street east of I-35.

The project should be complete no later than December, 2014, but the contract includes a 75-day contract incentive clause and could be completed as soon as Sept. 14.

Direct additional questions to John Clink, City of Norman Capital Projects Manager, at (405)366-5424.

Breaking news, severe weather alerts, AMBER alerts, sports scores from The Norman Transcript are available as text messages right to your phone or mobile device. You decide which type of alerts you want to receive. Find out more or to signup, click here.

1
Text Only | Photo Reprints
New and Developing

Headlines

Sports

Opinion

Features
Must Read

Editorials

Video
Kerry: Humanitarian Cease-fire Efforts Continue Raw: Corruption Trial Begins for Former Va Gov. The Carbon Trap: US Exports Global Warming UN Security Council Calls for Gaza Cease-fire Traditional African Dishes Teach Healthy Eating 13 Struck by Lightning on Calif. Beach Baseball Hall of Famers Inducted Israel, Hamas Trade Fire Despite Truce in Gaza Italy's Nibali Set to Win First Tour De France Raw: Shipwrecked Concordia Completes Last Voyage Raw: Sea Turtle Hatchlings Emerge From Nest Raw: Massive Dust Storm Covers Phoenix 12-hour Cease-fire in Gaza Fighting Begins Raw: Bolivian Dancers Attempt to Break Record Raw: Israel, Palestine Supporters Rally in US Raw: Air Algerie Flight 5017 Wreckage Virginia Governor Tours Tornado Aftermath Judge Faces Heat Over Offer to Help Migrant Kids Kangaroo Goes Missing in Oklahoma More M17 Bodies Return, Sanctions on Russia Grow
Business
Photos


Facebook