Safety requirements set for pipeline

WASHINGTON — Safety regulators have quietly placed two extra conditions on construction of TransCanada Corp.’s Keystone XL oil pipeline after learning of potentially dangerous construction defects involving the southern leg of the Canada-to-Texas project.

The defects — high rates of bad welds, dented pipe and damaged pipeline coating — have been fixed. But the federal Pipeline and Hazardous Materials Safety Administration wants to make sure similar problems don’t occur during construction of the pipeline’s controversial northern segment, which is on hold pending a decision by the Obama administration.

One condition requires TransCanada to hire a third-party contractor chosen by the pipeline safety agency to monitor the construction and make reports to the U.S. government on whether the work is sound.

The second requires TransCanada to adopt a quality management program to ensure “this pipeline is — from the beginning — built to the highest standards by both Keystone personnel and its many contractors.”

The conditions are buried near the end of the 26 appendices in a voluminous environmental impact statement on Keystone XL released by the State Department on Jan. 31.

Most of Appendix Z is devoted to 57 well-known “special conditions” that TransCanada agreed to three years ago. But conditions 58 and 59 are listed on an additional page.

“Everybody looked at that appendix and said, ‘Oh, 57 conditions. Move on.’ Well, there are a couple more there,” energy analyst Kevin Book said. “They just added them without saying anything.”

The new conditions were added four months after the pipeline safety agency sent TransCanada two warning letters last year about defects and other construction problems on the Keystone Gulf Coast Pipeline, which extends from Oklahoma to the Texas Gulf Coast.

“From the start of welding, TransCanada experienced a high weld rejection rate,” said one letter dated Sept. 26. Over 72 percent of welds required repairs during one week. In another week, TransCanada stopped welding work after 205 of 425 welds required repair.

Text Only | Photo Reprints
New and Developing

Headlines
Sports
Opinion

Features

Must Read

Editorials

Video
Obama Chides House GOP for Pursuing Lawsuit New Bill Aims to Curb Sexual Assault on Campus Russia Counts Cost of New US, EU Sanctions 3Doodler Bring 3-D Printing to Your Hand Six PA Cops Indicted for Robbing Drug Dealers Britain Testing Driverless Cars on Roadways Raw: Thousands Flocking to German Crop Circle At Least 20 Chikungunya Cases in New Jersey Raw: Obama Eats Ribs in Kansas City In Virginia, the Rise of a New Space Coast Raw: Otters Enjoy Water Slides at Japan Zoo NCAA Settles Head-injury Suit, Will Change Rules Raw: Japanese Soldiers Storm Beach in Exercises Raw: Weapons Fire Hits UN School in Gaza Raw: Rocket Launches Into Space With Cargo Ship Broken Water Main Floods UCLA Two Women Narrowly Avoid Being Hit by Train Crayola Announces Family Attraction in Orlando
Business
Photos


Facebook